Tuesday, August 4, 2009

Jonathan Law Addition Re-Approved, Board of Finance "Over Ruled"

Republican Alderman Raymond Vitali broke from his party and pushed through a $4 million Jonathan Law High School renovation project when the Board of Aldermen met Monday night.

Vitali had labored over the vote. He said last week that he planned to study plans and cost projections in the days leading up to the Board of Aldermen meeting, knowing that the pressure was on him to move the renovations forward, or to stop them in their track.

The aldermen needed to override a Board of Finance veto of the project by a two-thirds vote to get the project going. Democratic aldermen were united in their desire to approve the project. Republicans, except Vitali, stood beyond Mayor James Richetelli in opposing the addition now because they said the economy does not warrant such spending.

The Democrats, who hold a 9-6 majority on the board, needed one Republican to cross the line to give them the two-thirds voting power they needed.

“This is a very difficult situation,” Vitali said moments before the aldermen voted. “It seems to be the worst times and the best of times to go forward with this project.”

Vitali, a retired middle school principal, said he is sensitive to teachers who have to teach on carts because there is no classroom space for them, and he said it is the administration’s job to make sure staff is happy and that the building is adequate.

“I’ve made my mind up,” Vitali said.

Republican Alderman Scott Willey led the GOP opposition, charging that the project should not go forward in this economy.

“These are unprecedented economic times and you don’t go spending money you don’t absolutely have to spend,” Willey said. “Where’s the money going to come from to pay on what we borrow? We’re not reducing class size. We’re not increasing teachers. We’re still going to have teachers on carts even with the addition.”

Willey also criticized the process that led to approval of the $4 million bonding project. Typically, the mayor recommends bonding projects and the Board of Finance approves or denies them.

In this case, the Democratic aldermen took up the cause for teachers and parents who insisted it should move forward, approved it at last month’s Board of Aldermen’s meeting, and then forwarded it to the finance board, which rejected the plan.

“The mayor didn’t propose it; finance said ‘no don’t do it’,” Willey said. “This is wrong and it sets a terrible precedent.”

Parents and other school supporters defended the bonding request, however, arguing that bids for the addition came in $1 million lower than expected, interest rates are low and they expect state reimbursement rates to be less favorable in coming years.

“The truth is that the responsible course is to move forward now,” said Democratic mayoral candidate Genevieve Salvatore. “It’s fiscally irresponsible to delay this further.”

Jonathan Law High School Principal Janet Garagliano has said the school sorely needs more classrooms. She said 15 teachers would be working from carts next year, and the school is short two science labs.

The new addition would be a one-story, 12,000-square-foot structure consisting of nine classrooms, plus storage, according to Phil Russell, deputy supt. of operations for the Milford school system.

The school now contains 205,765 square feet. The addition would represent more than a 5% increase in square footage.

With Monday’s vote, the project is set to move forward, Russell said.

A contract is expected to be awarded the week of Aug. 17, following a 10-day appeal period. Construction will start in early September and will take about nine months to complete.

“Work will take place in an exterior courtyard,” said Bill Silver, of Silver Petrucelli and Associates, the main architects on the project. “So it won’t affect any classrooms.”

Original Post By Jill Dion

Tuesday, July 28, 2009

Alderman Raymond Vitali R5, May Hold Jonathan Law's Future In His Hands

The future of a $4 million addition to Jonathan Law High School rests in the hands of Alderman Raymond Vitali, R-5, after the Board of Finance rejected authorizing funds for the work Monday night.

The Finance Board’s 3-2 rejection means the request will be sent back to the Board of Aldermen. The aldermen will need a supermajority to approve the addition, and reverse the Finance Board’s decision.

Earlier this month, the aldermen voted 10-5 to approve creating a draft bond authorization, which was a critical first step toward allocating the $4 million for the work.

All nine Democrats and Vitali, a retired longtime school principal, approved creating the draft bond allocation, while the board’s remaining five Republicans voted against the project, saying a recession is not the right time to be borrowing funds.

In order for the aldermen to get a supermajority vote, Vitali would again need to break from his party and vote with the Democrats.

Vitali, who is aware of his role, stood up during the Finance Board meeting held at the Parsons Government Center Monday, and said, “I am the two-thirds vote.” He said the entire process has been “purely political,” but did not elaborate.

After the meeting Vitali declined to say how he’d vote, saying he needed to learn more about the city’s finances and “do some thinking.”

Before the Finance Board’s vote, Republican Mayor James L. Richetelli Jr. again reiterated his strong objection to borrowing any money, while the nation is in a historic recession.

He also said it sends a terrible message to borrow funds many residents are suffering financially.

Finance Board Chairman Jack Skudlarek said he had concerns that the aldermen, and not Richetelli, placed the project on the agenda calling it an “extraordinary” measure. Skudlarek said the mayor as the city’s chief executive officer places items on the agenda, and Richetelli said, while unprecedented, the move was legal according to the bond counsel.

Skudlarek also said he was not convinced there were any immediate health and safety concerns warranting that the project be approved now.

Proponents of the Law addition say the bids came in $1 million less than anticipated, and waiting would likely mean the city would receive less state reimbursement.

Jonathan Law Principal Janet Garagliano said the addition is needed because next year 15 teachers are projected to be using carts, which means they do not have their own classroom.

She said the school is short two science labs, and is looking to convert storage space into reading classrooms. Four classrooms have been converted from storage spaces in the school.

The work includes construction of a 12,234-square-foot addition including seven regular classrooms and two science laboratories in a ninth-grade wing.

Finance Board member Joseph Agro said the project should move forward because it’s likely costs will only increase in the future, but board member Joseph Fitzpatrick argued the bids are too high, and it’s likely the costs will drop.

Aldermanic Chairman Ben Blake, D-5, defended the aldermen’s actions saying typically the city spends $15 million annually on bond projects and by approving only $4 million for the Law addition it’s still “reining back considerably” the amount of money that is borrowed.

ORIGINAL BRIAN MCREADY POST CLICK HERE